CATALOG INFORMATION
|
Discipline and Nbr:
CONS 74 | Title:
CONST. SCHEDULING |
|
Full Title:
Construction Project Scheduling |
Last Reviewed:2/9/2015 |
Units | Course Hours per Week | | Nbr of Weeks | Course Hours Total |
Maximum | 1.50 | Lecture Scheduled | 1.50 | 17.5 max. | Lecture Scheduled | 26.25 |
Minimum | 1.50 | Lab Scheduled | 0 | 17.5 min. | Lab Scheduled | 0 |
| Contact DHR | 0 | | Contact DHR | 0 |
| Contact Total | 1.50 | | Contact Total | 26.25 |
|
| Non-contact DHR | 0 | | Non-contact DHR Total | 0 |
| Total Out of Class Hours: 52.50 | Total Student Learning Hours: 78.75 | |
Title 5 Category:
AA Degree Applicable
Grading:
Grade Only
Repeatability:
00 - Two Repeats if Grade was D, F, NC, or NP
Also Listed As:
Formerly:
Catalog Description:
Untitled document
Construction scheduling types are explored: bar charts, S-curves, logical sequencing, and network diagrams. Introduces the use of computers in documenting Critical Path Method (CPM) in scheduling. The role of the schedule in project management is discussed.
Prerequisites/Corequisites:
Course Completion of CONS 70A ( or CONS 70)
Recommended Preparation:
Limits on Enrollment:
Schedule of Classes Information
Description:
Untitled document
Construction scheduling types are explored: bar charts, S-curves, logical sequencing, and network diagrams. The use of computers in documenting Critical Path Method (CPM) schedules is introduced. The role of the schedule in project management is discussed.
(Grade Only)
Prerequisites:Course Completion of CONS 70A ( or CONS 70)
Recommended:
Limits on Enrollment:
Transfer Credit:CSU;
Repeatability:00 - Two Repeats if Grade was D, F, NC, or NP
ARTICULATION, MAJOR, and CERTIFICATION INFORMATION
Associate Degree: | Effective: | | Inactive: | |
Area: | | |
|
CSU GE: | Transfer Area | | Effective: | Inactive: |
|
IGETC: | Transfer Area | | Effective: | Inactive: |
|
CSU Transfer: | Transferable | Effective: | Spring 2009 | Inactive: | Fall 2021 |
|
UC Transfer: | | Effective: | | Inactive: | |
|
C-ID: |
Certificate/Major Applicable:
Both Certificate and Major Applicable
COURSE CONTENT
Outcomes and Objectives:
At the conclusion of this course, the student should be able to:
Untitled document
Upon completion of this course the student will:
1. Identify information needed to schedule a construction project.
2. Determine sequence of individual construction activities.
3. Document typical network pattern for sequence of activities.
4. Interpret bar charts, S-curves, logical sequencing and network diagrams.
5. Develop a project schedule using the Critical Path Method.
Topics and Scope
Untitled document
I. Planning for construction
A. Activity information needed to construct a schedule
B. Time information needed to construct a schedule
II. Scheduling methods
A. Bar charts
B. S-curves
C. Logical sequencing
D. Network diagrams
E. Fundamentals of Critical Path Method (CPM) scheduling
III. Developing a project schedule
A. Diagramming alternatives
B. Using CPM
IV. Using schedules for project management
A. Interpreting project schedule
B. Interpreting summary bar chart
C. Interpreting project status report
D. Interpreting cost control information
Assignments:
Untitled document
Reading: 20 pages per week
Homework: 3-4 problems per week
Skill demonstration: weekly construction schedule exercises
Quizzes: 2-4
Final exam
Methods of Evaluation/Basis of Grade.
Writing: Assessment tools that demonstrate writing skill and/or require students to select, organize and explain ideas in writing. | Writing 0 - 0% |
None | |
This is a degree applicable course but assessment tools based on writing are not included because skill demonstrations are more appropriate for this course. |
|
Problem solving: Assessment tools, other than exams, that demonstrate competence in computational or non-computational problem solving skills. | Problem Solving 20 - 30% |
Weekly homework assignments | |
Skill Demonstrations: All skill-based and physical demonstrations used for assessment purposes including skill performance exams. | Skill Demonstrations 40 - 50% |
Weekly construction schedule exercises | |
Exams: All forms of formal testing, other than skill performance exams. | Exams 20 - 30% |
Objective exams, multiple choice, and final exam | |
Other: Includes any assessment tools that do not logically fit into the above categories. | Other Category 0 - 0% |
None | |
Representative Textbooks and Materials:
Untitled document
Microsoft Office Project 2003 Inside Out, by T. Stover, Microsoft Press (2003)
Dynamic Scheduling with MSOffice Project 2007: The Book by and for Professionals, by R. Ambriz, J.Ross Publishing, Inc. (2008)
Instructor prepared materials